VIRGINIA BEACH, Va. (AP) — A replenishment project which put millions of dollars' worth of sand on a portion of the Virginia Beach Oceanfront appears to have withstood Hurricane Dorian.

The Virginian-Pilot reports city coastal programs manager Dan Adams says visual inspections of area beaches have been under way since the weekend. He says erosion from wind and wave action is "minor." Surveys will be conducted over the next few weeks to determine how much sand was lost.

Great Lakes Dredging and Dock Co. completed 75% of a $22.6 million sand replenishment project before it had to stop at the end of August. Dredging restrictions are in place through mid-November as sea turtles migrate.

The company is scheduled to return to Virginia Beach on Nov. 15 to complete the project.


PHOTOS: Satellite, aerial images of N.C. before and after Hurricane Dorian

Get the Virginia Politics Insider email update every evening during the GA and weekly all year

* I understand and agree that registration on or use of this site constitutes agreement to its user agreement and privacy policy.

Copyright 2019 The Associated Press. All rights reserved. This material may not be published, broadcast, rewritten or redistributed.

Load comments

You must be a full digital subscriber to read this article You must be a digital subscriber to view this article.