pvcc

Piedmont Virginia Community College is planning to build the Advanced Technical Training Center across the road from the school’s main building.

CHARLOTTESVILLE — Commuters on Interstate 64 soon may have a new signpost of sorts for Piedmont Virginia Community College: rather than a small and easy-to-miss sign near the road, they will be able to see the planned Advanced Technical Training Center.

The center will rise “like a lantern” up the side of a hill, according to Jim Kovach, a senior associate with VMDO, which is under contract to create architectural drawings for the $20 million building. The center, slated for completion by 2022, will house future science and technical labs, administrative offices, a café, and student study space.

Piedmont’s board reviewed and approved schematic designs for the building at a special meeting Wednesday. The Virginia Community College System has approved money for site work and construction.

The building will be 45,000 square feet, and range from two to three stories. It will sit along the Albemarle County campus’ main College Drive, directly across from the Main Building.

“This will really be a beating, thriving heart of the campus, we hope,” Kovach told the board as he described the drawings.

Students, faculty and staff will be able to walk over a short bridge and into the new building. Half the building will be devoted to administrative and instructional space; the other half, on the other side of the open lobby, will be event and activity space. The ground floor — with classrooms, a cyberlab and event space — will open out to a 106-spot parking lot.

The second floor of the building will hold administrative offices and will relocate the Main Building’s café, according to the plans. The third floor, situated on one half of the building, will also contain meeting and office spaces for student clubs and organizations.

Albemarle and state architectural review boards still must review the proposed design. Preliminary design approvals are expected by the spring of 2020, with construction projected to begin in November 2020 and finish in 2022.

Recommended for you

Commenting is limited to Times-Dispatch subscribers. To sign up, click here.
If you’re already a subscriber and need to activate your access or log in, click here.

Load comments

You must be a full digital subscriber to read this article You must be a digital subscriber to view this article.